Superfund Site
Client:
San Bernadino, CA
Category:
Date:
2010-2012
Status:
Completed
Superfund Site, San Bernadino, CA
Superfund Site, San Bernadino, CA
PROJECT HIGHLIGHTS
REGULATORY AGENCY – United States Environmental Protection Agency
CONTAMINANTS OF CONCERN – Perchlorate
REMEDIATION STRATEGY – Water Reuse, Pump & Treat
SPECIAL CHALLENGES – Tight Time Line, Very Large System
Superfund Site, San Bernadino, CA
Project Summary
Significant rocket, flare, and pyrotechnics site that resulted in the contamination of a major municipal supply system, and involved numerous responsible parties. Murex performed hydrogeologic studies, allocated portioned responsibility to various entities, and prepared designs and construction cost estimates identifying cost contributions based on the different contributing chemical agents and their sources. The Federal EPA was the lead agency.

The challenges faced with this project is the tight time line and the need to design three separate treatment configurations, and the preparation of H20 engineering cost estimates. The groundwater treatment system was required to accommodate a maximum capacity of 3200 gpm. The end use of the treatment is for drinking water.